Reply To: Project Time Management Processes

#2997 Reply

Mandy

Sequencing Activities

1-nvolves reviewing activities and determining dependencies
2-A dependency or relationship is the sequencing of project activities or tasks
3-You must determine dependencies in order to use critical path analysis

Three types of Dependencies

Mandatory dependencies: inherent in the nature of the work being performed on a project, sometimes referred to as hard logic

Discretionary dependencies: defined by the project team., sometimes referred to as soft logic and should be used with care since they may limit later scheduling options

External dependencies: involve relationships between project and non-project activities