Program Evaluation and Review Technique (PERT) is a network analysis technique used to estimate project duration when there is a high degree of uncertainty about the individual activity duration estimates.
PERT weighted average =
(Optimistic time + (4 × Most likely time) + Pessimistic time) / 6