Network Diagrams | Project Time Management

Home Forums Official Forum- Navsingh Object Oriented Software Engineering Network Diagrams | Project Time Management

This topic contains 2 replies, has 1 voice, and was last updated by  Mandy 2 years, 3 months ago.

  • Author
    Posts
  • #2998 Reply

    Mandy

    Network Diagrams | Project Time Management

    Network diagrams are the preferred technique for showing activity sequencing

    A network diagram is a schematic display of the logical relationships among, or sequencing of, project activities

    Two main formats are the arrow and precedence diagramming methods

  • #2999 Reply

    Mandy

    Critical Path Method

    CPM is a network diagramming technique used to predict total project duration

    A critical path for a project is the series of activities that determines the earliest time by which the project can be completed

  • #3000 Reply

    Mandy

    Calculating the Critical Path

    1-First develop a good network diagram

    2-Add the duration estimates for all activities on each path through the network diagram

    3-The longest path is the critical path

    4-one or more of the activities on the critical path takes longer than planned, the whole project schedule will slip unless the project manager takes corrective action

Reply To: Network Diagrams | Project Time Management