Program Evaluation and Review Technique (PERT)

Home Forums Official Forum- Navsingh Object Oriented Software Engineering Program Evaluation and Review Technique (PERT)

This topic contains 1 reply, has 1 voice, and was last updated by  Mandy 2 years, 5 months ago.

  • Author
    Posts
  • #3001 Reply

    Mandy

    Program Evaluation and Review Technique (PERT)

    PERT is a network analysis technique used to estimate project duration when there is a high degree of uncertainty about the individual activity duration estimates
    PERT uses probabilistic time estimates
    duration estimates based on using optimistic, most likely, and pessimistic estimates of activity durations, or a three-point estimate

  • #3002 Reply

    Mandy

    Program Evaluation and Review Technique (PERT) is a network analysis technique used to estimate project duration when there is a high degree of uncertainty about the individual activity duration estimates.
    PERT weighted average =
    (Optimistic time + (4 × Most likely time) + Pessimistic time) / 6

Reply To: Program Evaluation and Review Technique (PERT)
Your information:




Official Forum

This is the Official Forum of Navsingh a community that helps you find answers to all of your problems,they can be Java/programming,wordpress,android, android programming, seo related or technology related